Construction of a factory complex with a floor area of approx. 30,000 m² at EPZ, Biyagama.
CLIENT
Paxar Lanka (Pvt) Ltd
PROJECT DURATION
6 Months
PROJECT COST
Rs. 35 Million
PROJECT STATUS
Completed in August 2000
ARCHITECTS & STRUCTURAL ENGINEERS
Buildmart Lanka (Pvt) Ltd.
MAIN CONTRACTORS
Buildmart Lanka (Pvt) Ltd.
BACK GROUND
The service of a Project Manager was requested by the Client to effectively administer the project on a Design-build basis and control schedule and cost in order to complete the project within the stipulated time and cost targets
SERVICE
Prepare tender documents and invite tenders from selected contractors.
Evaluate Tenders and make recommendation with regard to award of contract.
Prepare and establish a cost control system.
Co-ordinate & monitor the project activities to complete the project within cost and time limits.