PROJECT | Construction of a 21 storey office complex situated at 28 St Michael’s Road, Colombo 3. |
CLIENT | Bank of Ceylon |
PROJECT DURATION | 18 Months |
PROJECT COST | Rs. 800 Million |
PROJECT STATUS | Completed in September 1997 |
ARCHITECTS & STRUCTURAL ENGINEERS | The Design Group Five International Ltd |
STRUCTURAL | Stems Consultants |
MAIN CONTRACTORS | Mitsui |
BACK GROUND | The Client requested for services of a Project Manager,
In order to complete the project within the stipulated time and cost targets. |
SERVICE |
NOTE: In addition to the above-mentioned services, at the request of Bank of Ceylon, LAN Management Development Service (LANMDS) carried out a comprehensive study on the rents chargeable for the office complex, constructed at Kollupitiya. The study report was submitted in August 1995 |